Construction progress is where off-plan reality diverges from marketing most often. Verifying it protects both your money and your timeline.
Define the milestones
Agree on what each stage means before comparing claims: foundation, frame/structure, roofing, MEP (mechanical, electrical, plumbing), finishing, completion. Vague stage names make every claim unfalsifiable.
Inspect, with dates
Visit the site or send an independent representative. Photograph the same viewpoints each time, with timestamps. Compare what is standing against the claimed stage — a claimed "finishing" stage should show fitting-out, not bare blockwork.
Compare claims against a claimed baseline
The developer's claimed stage is a claim. The verified stage — what an inspection confirmed, on a date — is a finding. Keep the two visibly separate. A discrepancy is not automatically fraud; construction moves fast. But a large unexplained gap, or claims that never move, deserve hard questions.
Monitor between payments
Tie payment milestones to verified progress, so each payment has a checkpoint behind it. If a scheduled verification shows less progress than expected, you can pause before paying.
Use records, not memory
A credible progress record is a table: each milestone, what the developer reported, what the platform verified, and the date of the last verification — with renewal flagged when a check goes stale. On offplanverify, every property's evidence trail carries exactly this: construction checkpoints with verified dates, and a note when verification requires renewal because the review date has passed. Read the dates, and treat "last verified" as exactly that.